Business programs count days that are not weekends and not holidays, group dates into weeks and quarters, and compute ages. This lesson adds working days to a date, counts them between two dates, finds ISO week numbers and the end of a month, and computes an age.

What you will learn#

The tutorial Dates and times and the tutorial Calendars and dates showed the date types and the calendar of a month. This lesson is about the rules that business programs add.

The program#

samples/UsingDotNet/tutorials/ch03_workdays.ring
# working days - adding business days, skipping weekends and holidays, week numbers, quarters, month ends and an age
load "dotnet.ring"

using {
	"System"
	"System.Globalization"
}

# the holidays of this example (fixed dates written as year-month-day)
aHolidays = [ "2030-01-01", "2030-12-25", "2030-12-26" ]

func main

	# 1. The day of the week. DayOfWeek is a text: "Monday" ... "Sunday". Many countries have another weekend (Friday and Saturday), so the
	#    weekend is a list in one place.
	oDate = makeDate(2030,3,9)
	? "1. " + oDate.Format("yyyy-MM-dd") + " is a " + oDate.DayOfWeek + ", weekend: " + yesNo(isWeekend(oDate))
	? "   the days of the week of 11-17 March 2030:"
	cLine = ""
	for i = 11 to 17
		cLine += makeDate(2030,3,i).Format("ddd d") + "  "
	next
	? "   " + cLine

	# 2. Adding days is simple (AddDays), and adding WORKING days is a loop that skips the weekend and the holidays
	oStart = makeDate(2030,3,7)                         # a Thursday
	? nl + "2. from Thursday " + oStart.Format("yyyy-MM-dd") + ":"
	? "   + 1 calendar day:  " + oStart.AddDays(1).Format("ddd yyyy-MM-dd")
	for nDays in [ 1, 2, 5, 10 ]
		? "   + " + padRight("" + nDays,2) + " working days: " + addWorkdays(oStart,nDays).Format("ddd yyyy-MM-dd")
	next

	# 3. Holidays move the result. 2030-12-24 is a Tuesday; the 25th and 26th are holidays, and the 28th and 29th the weekend.
	oEve = makeDate(2030,12,24)
	? nl + "3. holidays: 3 working days after " + oEve.Format("yyyy-MM-dd") + " is " + addWorkdays(oEve,3).Format("ddd yyyy-MM-dd") + " (the 25th, 26th, 28th and 29th do not count)"

	# 4. Counting the working days between two dates (the first day is included, the last is not)
	? nl + "4. working days from 2030-03-01 to 2030-04-01: " + countWorkdays(makeDate(2030,3,1),makeDate(2030,4,1))
	? "   working days in the year 2030: " + countWorkdays(makeDate(2030,1,1),makeDate(2031,1,1))

	# 5. Week numbers. The ISO week starts on Monday, and week 1 is the week with the first Thursday of the year: so the first days of
	#    January can belong to the last week of the year before, and the last days of December to week 1 of the next year.
	? nl + "5. ISO weeks:"
	for aItem in [ [2030,1,1], [2030,3,9], [2030,12,30], [2027,1,1] ]
		oD = makeDate(aItem[1],aItem[2],aItem[3])
		? "   " + oD.Format("yyyy-MM-dd ddd") + "  week " + isoWeek(oD) + " of " + isoYear(oD)
	next

	# 6. Quarters and the end of a month. DaysInMonth knows the leap years.
	? nl + "6. quarters and month ends:"
	for nMonth = 1 to 12 step 4
		? "   month " + padRight("" + nMonth,3) + "quarter " + (floor((nMonth - 1) / 3) + 1) + ", the month has " + daysInMonth(2030,nMonth) + " days"
	next
	? "   February has " + daysInMonth(2030,2) + " days in 2030 and " + daysInMonth(2032,2) + " in 2032"
	? "   the last day of February 2032 is " + makeDate(2032,2,daysInMonth(2032,2)).Format("yyyy-MM-dd ddd")

	# 7. An age: the years between a birth date and a day, one less when the birthday of this year did not come yet
	? nl + "7. ages on 2030-03-09:"
	for aItem in [ [2000,3,9], [2000,3,10], [1990,12,31], [2030,3,9] ]
		? "   born " + padRight(makeDate(aItem[1],aItem[2],aItem[3]).Format("yyyy-MM-dd"),11) + "age " + ageOn(makeDate(aItem[1],aItem[2],aItem[3]),makeDate(2030,3,9))
	next

func makeDate nYear,nMonth,nDay

	return new DateTime(nYear,nMonth,nDay)

# the weekend in one place (Saturday and Sunday here; use ["Friday","Saturday"] for the countries with that weekend)
func isWeekend oDate

	cDay = "" + oDate.DayOfWeek
	return cDay = "Saturday" or cDay = "Sunday"

func isHoliday oDate

	return find(aHolidays,oDate.Format("yyyy-MM-dd")) > 0

func isWorkday oDate

	return not isWeekend(oDate) and not isHoliday(oDate)

# n working days after a date (the date itself does not count)
func addWorkdays oDate,nDays

	oCurrent = oDate
	nLeft = nDays
	while nLeft > 0
		oCurrent = oCurrent.AddDays(1)
		if isWorkday(oCurrent)
			nLeft--
		ok
	end
	return oCurrent

func countWorkdays oFrom,oTo

	nCount = 0
	oCurrent = oFrom
	while oCurrent.CompareTo(oTo) < 0
		if isWorkday(oCurrent)
			nCount++
		ok
		oCurrent = oCurrent.AddDays(1)
	end
	return nCount

func isoWeek oDate

	return new ISOWeek().GetWeekOfYear(oDate)

func isoYear oDate

	return new ISOWeek().GetYear(oDate)

func daysInMonth nYear,nMonth

	return new DateTime(nYear,nMonth,1).DaysInMonth(nYear,nMonth)

# the years between two dates, minus one when the birthday of that year has not come yet
func ageOn oBirth,oDay

	nAge = oDay.Year - oBirth.Year
	if oDay.Month < oBirth.Month or (oDay.Month = oBirth.Month and oDay.Day < oBirth.Day)
		nAge--
	ok
	return nAge

func yesNo lValue

	if lValue
		return "yes"
	ok
	return "no"

func padRight cText,nWidth

	return cText + copy(" ",nWidth - len(cText))
Output
1. 2030-03-09 is a Saturday, weekend: yes
   the days of the week of 11-17 March 2030:
   Mon 11  Tue 12  Wed 13  Thu 14  Fri 15  Sat 16  Sun 17  

2. from Thursday 2030-03-07:
   + 1 calendar day:  Fri 2030-03-08
   + 1  working days: Fri 2030-03-08
   + 2  working days: Mon 2030-03-11
   + 5  working days: Thu 2030-03-14
   + 10 working days: Thu 2030-03-21

3. holidays: 3 working days after 2030-12-24 is Tue 2030-12-31 (the 25th, 26th, 28th and 29th do not count)

4. working days from 2030-03-01 to 2030-04-01: 21
   working days in the year 2030: 258

5. ISO weeks:
   2030-01-01 Tue  week 1 of 2030
   2030-03-09 Sat  week 10 of 2030
   2030-12-30 Mon  week 1 of 2031
   2027-01-01 Fri  week 53 of 2026

6. quarters and month ends:
   month 1  quarter 1, the month has 31 days
   month 5  quarter 2, the month has 31 days
   month 9  quarter 3, the month has 30 days
   February has 28 days in 2030 and 29 in 2032
   the last day of February 2032 is 2032-02-29 Sun

7. ages on 2030-03-09:
   born 2000-03-09 age 30
   born 2000-03-10 age 29
   born 1990-12-31 age 39
   born 2030-03-09 age 0

How it works#

The weekend and the holidays#

DayOfWeek gives the name of the day as a text. The function isWeekend compares it with "Saturday" and "Sunday"; some countries have a weekend on Friday and Saturday, and then only this function changes. The holidays are a Ring list of dates written as year-month-day, and isHoliday looks for the date in it. Real programs keep the holidays in a file or a table for each country and year (and some holidays, like Easter, move: they come from a rule, not from a fixed date).

Adding working days#

There is no formula that handles weekends and holidays, so addWorkdays does what a person does: it steps one day at a time and counts only the days that are working days. From a Thursday, 2 working days is the next Monday. The date itself does not count. Around 25 December 2030 (a Wednesday) the result jumps over the holidays and the weekend: 3 working days after the 24th is the 31st.

Counting between two dates#

countWorkdays walks from the first date up to, but not including, the second one, and counts the working days: that is a half-open range, the same rule as in most loops. The year 2030 has 261 weekdays and 3 holidays on weekdays, so 258 working days. (Walking day by day is fast enough for a few years; for a very long range count whole weeks first: each week has 5 working days.)

ISO weeks#

The ISO week starts on Monday, and week 1 is the week with the first Thursday of the year. So 1 January can belong to the last week of the year before (1 January 2027 is in week 53 of 2026) and the last days of December can belong to week 1 of the next year (30 December 2030 is in week 1 of 2031). That is why the function gives the week and the year of the week: ISOWeek.GetWeekOfYear and ISOWeek.GetYear. A report by week uses the pair, not the calendar year.

Quarters and month ends#

The quarter of a month is floor((month - 1) / 3) + 1. DateTime.DaysInMonth(year, month) knows the leap years (February 2032 has 29 days), so the last day of a month is the date with that day number; no program should have a table of month lengths.

An age#

The age is the difference of the years, minus one if the birthday of this year has not come. Someone born on 9 March 2000 is 30 on 9 March 2030, and someone born the next day is still 29. Subtracting the days and dividing by 365 is wrong: the leap days add up.

What you learned#

Exercises#

  1. Write previousWorkday(date) and nextWorkday(date).
  2. Write lastWorkdayOfMonth(year, month).
  3. Add Easter Monday: compute Easter Sunday with the Gregorian algorithm and add one day.
  4. Print a calendar for one ISO week: the seven dates and which are working days.

Next#

Cultures

RingDotNet — use .NET classes and methods from Ring programs. Screenshots and output on these pages come from the real samples.